Load out 4th pedestal

The load out of the 4th pedestal took place after a slight delay due to storm Poly. On Wednesday, the 5th of July the load out could not take place due to too much wind, however on Thursday the 6th of July the weather was suitable and Hollandia Systems, in cooperation with HEBO Maritiemservice, successfully placed the pedestal on the pontoon for transport to the customer.

The pedestal will be installed on the deck of a ship and serve as a base for a motion compensated walkway to wind turbines and offshore platforms. With a height of 7.5 meters, the pedestal can be raised to 12.5 meters using a modular intermediate piece.

This pedestal has a total weight of 85,000 kg and despite the great weight and complexity of the construction, Hollandia Systems managed to complete this pedestal within an exceptionally short delivery time of 100 days.

With the load out successfully completed, the pedestal is ready to be transported to the customer.