Transport 4th pedestal towards conservation
Today we took an important step in our construction project. The 4th pedestal chassis was successfully transported to the preservation hall.
After conserving the pedestal, we have 2 more weeks to install the toolbox, upper frame, all grids and secondary steel. This is an essential phase to complete the project.
We have scheduled our load-out for July the 5th. This means that on that day we want everything finished and ready for the next phase of our project.